The process of repairs and maintenance of units and facilities, based on the coordination made with Asaluyeh Petrochemical Company – Green Tanks Complex, began on Friday, March 21, 2025, with 85 personnel and is scheduled for 30 working days.(21/March/2025)

Commencement of the project to repair and maintain Bandar Imam Petrochemical Facilities and Units – Faravaresh 2 Complex with the presence of approximately 240 specialized personnel from the beginning of March (19/February/2025)

The overhaul of the third phase ammonia and urea units of Pardis Petrochemical Company was carried out with 532 maintenance programs over a period of 12 days.

The third phase units were taken out of service on Tuesday, January 28, and maintenance activities began on January 10. Thanks to God and the efforts of all colleagues, the overhaul operations were completed as planned on January 11

( 12/January/2025)

Major repairs of Bandar Imam Petrochemical Plant _ Central Workshops.(9/June/2024)

The start of the repair and maintenance contract for the Apadana Petrochemical Company’s complex and methanol units with the presence of approximately 200 Sena Andisheh personnel.(3/September/2024)

The collection of the HD unit of Bandar Imam Petrochemical Company began for three months on 2024 /11 /9 and ended on 2025 / 2/7 .